CONSTRUCTION OF A CONTAINERIZED POWER SUBSTATION AT PCC ROKITA S.A.

Investor

PCC Rokita S.A.

Ordering party

PCC Rokita S.A.

Scope of work

  • Modernization of the existing medium-voltage (MV) switchgear
  • Execution of excavations and directional drilling under roads within an active chemical production facility
  • Execution of the power supply for the new transformer station
  • Supply and installation of a complete transformer station
  • Supply and installation of a 12-bay MV switchgear
  • Supply and installation of two 2500kVA transformers
  • Execution of gas-tight/water-tight system sealings at building entrances
  • Supply and installation of 4000A busways (2 sets)
  • Supply and installation of RG38 (7-bay), RPWS, R110DC, RS1 switchgears and meter boards
  • Execution of telemechanics for the new transformer station
  • Execution of the fire alarm system (SAP) (including integration into the existing system)
  • Execution of complete fire-rated penetrations
  • Execution of complete grounding and equipotential bonding installations
  • Execution of low-voltage (LV) cabling (reconnecting existing devices to the new transformer station)
  • Execution of signaling and control cabling
  • Execution of fiber optic cabling
  • General construction works
  • Land surveying services
  • Parameterization and commissioning of MV and LV switchgears
  • Execution of complete testing and control-measurement works