CONSTRUCTION OF THE BRZESZCZE COGENERATION PLANT 5.7 MW
Strona główna » CONSTRUCTION OF THE BRZESZCZE COGENERATION PLANT 5.7 MW
Investor
Grupa Tauron Dystrybucja Serwis S.A.
Ordering party
Zakład Górniczy Brzeszcze - Tauron Wydobycie S.A.
Scope of work
Comprehensive construction and assembly works related to the installation and utility connection of the supplied cogeneration units (2x 2.7 MW)
Heat evacuation from the cogeneration units and supply of gas feed
Construction of 2.5 km of low- and medium-pressure gas pipelines, central heating (CO), and water and sewage (WOD-KAN) networks
Power evacuation from the cogeneration units and installation of MV cable lines (2.7 km), including the construction of MV and LV switchgear and switchboards
see more
see more
Industry
CONSTRUCTION OF PRODUCTION PLANT WITH INFRASTRUCTURE FOR GATES POLSKA