PHASE 1: Electrical installations supply and assembly:
2000 kVA 15/0.4 kV Al./Al transformer
3200 A Al. busbar between the transformer and the main LV switchgear
400 kVAr capacitor bank with 7% reactors main LV switchgear (RGNN)
branch LV switchgears
400 kVAr capacitor bank with 7% reactors
central battery system for buildings 4 and 6a
health and safety (BHP) equipment
UPS unit
galvanized cable trays
basic lighting fixtures
emergency lighting fixtures
maintenance socket sets
PMS system
lightning protection system
equipotential system
grounding system
External electrical installations – dismantling, supply and assembly:
dismantling of existing MV and LV cable lines
external LED lighting
Execution of structured cabling network
Execution of fire alarm system (SAP)
PHASE 2 Technology cabling:
Supply and installation of cable trays
Supply and laying of LV and control cables including connection
Assembly of distribution cabinets, patch panels, control boxes, maintenance switches, signaling boxes, signalers, safety switches, etc.
Post-installation measurements
As-built documentation
Participation in commissioning
see more
see more
Energy sector
CONSTRUCTION OF A GAS UNIT BASED ON A GAS TURBINE WITH A HEAT RECOVERY STEAM GENERATOR AT PGE EC S.A. KIELCE CHP BRANCH AND SERVICE AGREEMENT FOR THE GAS TURBINE – 8 MWe AND 12.5 MWt